This week, relaid flagstones have created a ramp that now provides disabled access to the student post room

New ducts have been installed to accommodate the electrical installation and to provide infrastructure for the future. 

Recycled foamed glass gravel has been installed as a base for the new lime screed in the main reception lobby. 

30 original flagstones have been relaid to raise pavement levels, creating a ramp to the student post room to provide disabled access.

The second archway is nearing completion, with the facade facing stone now to be completed after the removal of the temporary works. 


Ian Stokes, Master of Works

Update 21: 14 August 2020