Inside the Lodge, painting is continuing, and the paving area in the new Reception Area has been completed

Final coats of paint have been applied to the leaded lights prior to the installation of secondary glazing, and radiators have been installed in the student post area. 

A glazing track has been installed in the meeting rooms, so that glass sizes can be confirmed and cut to size off site. 

The new York paving in the Reception Area is now complete, ready to receive the new stone plinth upstand. 


Ian Stokes, Master of Works

Update 26: 25 September 2020