Internal areas are approaching completion, along with the second archway, while we're about to start work on a new ramp to the post room.

The second archway is progressing, with the infill stonework nearly complete. 

The joinery in the Parcel Room and Student Post Room is nearing completion. The wall panelling and windows in the Welfare Area have been stripped back, and filling and decorating is now underway.

Next week we are working on the new ramp to the post room, which means that access between Front Quad and Dolphin Quad will involve a diversion. 


Ian Stokes, Master of Works

Update 20: 7 August 2020