One of the archways into the new reception area is almost complete

The completion of the first entrance archway is expected next week, with the continuation of the first fix electrical installation in the front reception area. 

Plaster repairs are continuing, after which we'll allow two weeks for curing and drying before the decoration can commence. 

Decoration in the student post room and parcel room has continued, and we've started to install the plinths for the student pigeonhole units. 


Ian Stokes, Master of Works

Update 15: 3 July 2020