Work continues on internal decorations in the renovated Lodge building

Lime screed has been installed for the flooring in the reception area, and, during the electrical shutdown on 19 August, a new mains panel was also installed. 

Cabinets have been fitted for the welfare kitchenette, in preparation for measurement for the oak facings. 

The ceiling in the reception area has had plasterboard installed and a plaster finish applied. 

The first coat of lime plaster has been applied to the internal side of the new stonework surrounding the new archways, providing the entrance and exit to the reception area. 

Decorations have also been added to the external windows. 


Ian Stokes, Master of Works

Update 22: 27 August 2020