Some visible recent changes in the Lodge include the installation of a steelwork at the main entrance, and continuing work on the windows and electrics.

The temporary works installation to the main entrance has been completed. This is a significant amount of steelwork, just in use temporarily, but given the weight of the tower above it is considered a good precaution. It is a very time-consuming process to insert each RSJ one at a time. 

We've continued with the window overhauls, ready for decoration, and have also progressed with first fix electrics and establishing cable routes. 


Ian Stokes, Master of Works

Update 11: 29 May 2020