Update 9: 15 May 2020
The temporary works and propping are just about in to provide for further safe removal of sections of walls to form the new openings.
We continue to work on the first fix electrical, have agreed the extent of defective lime plaster repairs and have started work on its removal, and the partitions in the post room are now taking shape.
Ian Stokes, Master of Works