Update 25: 18 September 2020
The existing York flag stones have been reinstalled following duct installation and temporary works.
A final coat of lime plaster has been applied to the archway wall, and the installation of new York stone flooring is underway in the Reception area.
The fire alarm cupboard has been installed, alongside the relocation of the fire alarm panel.
Oak panelling has continued to be installed in the meeting room, while, in the kitchenette, oak decor end panels, pelmets and doors are underway.
Ian Stokes, Master of Works