We're now getting onto some of the works necessary to finish the project.

Underground ducts have been installed for future use, as well as a fibre link following the existing cable route. 

There has been containment for electrics to the new fuse board, and the existing stone surround to the fireplace in the student post room has been cleaned and repointed where required. 

Second fix carpentry has continued in the welfare area, and preparation work and decoration has been carried out in the reception area. 

Next week, we'll be continuing with this prep work and decoration, as well as the second fix carpentry in the welfare area, while also carrying on with lime plastering in the reception area. 


Ian Stokes, Master of Works

Update 23: 4 September 2020